5. Project budget realization

On 31.7.2013, 58,3% of all budgeted costs were spent. A summary of costs can be found from OTR_budget_07_2013. NB! The section 6 is also related to the budget and costs.

Please leave a comment when necessary. Write your initials in the end of your comment.

2 Comments

  1. Matti Rantala
    8.9.2013 at 9.08 ·

    It looks like that we are on good shape and the project can be carried to the aim without major economical problems.

  2. Saila Linnahalme
    4.9.2013 at 10.06 ·

    Ok!
    sl